3D3-17054-BOQ for Stortstrom Bridge
N.E. 17054
BOQ for Stortstrom Bridge
ACCIONA
Date: 2017
Vordingborg, Denmark
Length: 3820 m
Global budget: N/A €
Budget of the tasks undertaken: N/A €
Tasks undertaken:
3D3-17052-Structural Engineering and technical assistance for desalination plant
N.E. 17052
Structural Engineering and technical assistance for desalination plant
INTECSA-INARSA
Date: 2017
Atacama, Chile
Area: WORK-IN-PROGRESS m²
Global budget: N/A €
Budget of the tasks undertaken: N/A €
Tasks undertaken: Basic Engineering. Detail Engineering.
3D3-17020-Architectural, MEP and Structural Engineering review and technical assistance for the refurbishment of an administrative Building in Cedaceros Street
N.E. 17020
Architectural, MEP and Structural Engineering review and technical assistance for the refurbishment of an administrative Building in Cedaceros Street
BUREAU VERITAS
Date: 2017
Madrid, Spain
Area: 2711 m²
Global budget: N/A €
Budget of the tasks undertaken: N/A €
Tasks undertaken: Project Review
3D3-17019-BOQ of IFC drawings in Toowomba
N.E. 17019
BOQ of IFC drawings in Toowomba
NEXUS
Date: 2017
Queensland, Australia
Area: WORK-IN-PROGRESS m²
Global budget: WORK-IN-PR MM €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken:
3D3-15028-Quantity Takeoffs for the Drainages, Linemarking and Fencing in Warrell Creek to Nambucca Heads Highway
N.E. 15028
Quantity Takeoffs for the Drainages, Linemarking and Fencing in Warrell Creek to Nambucca Heads Highway
PACIFIC AFJV
Date: 2015
Warrell Creek. Australia
Length: 19510 m
Global budget: AU.$ 5.50M €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken: Studies and Reports.
3D3-13011-Structual engineering for seven stormwater detention vaults
N.E. 13011
Structual engineering for seven stormwater detention vaults
ACCIONA Infraestructuras
Date: 2013
Ferrol, La Coruña. Spain
Area: 11387 m²
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Detail Engineering. Recalculation and expert evaluation
3D3-12017-Civil engineering preliminary draft for extension of CCGT Barranco III
N.E. 12017
Civil engineering preliminary draft for extension of CCGT Barranco III
IDOM
Date: 2012
Gran Canaria. Spain
Area: 16577 m²
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Preliminary drafts. Basic Engineering
3D3-12015-B-Civil and structural engineering services for biomass power plant in Ghana
N.E. 12015-B
Civil and structural engineering services for biomass power plant in Ghana
POYRY - HEYMO
Date: 2012
Atebubu. Ghana
Area: WORK-IN-PROGRESS m²
Global budget: WORK-IN-PR MM €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-12015-A-Civil and structural engineering services for Vopak industrial plant enlargement
N.E. 12015-A
Civil and structural engineering services for Vopak industrial plant enlargement
POYRY - HEYMO
Date: 2012
Callao. Peru
Area: WORK-IN-PROGRESS m²
Global budget: WORK-IN-PR MM €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-10017-Electrical and Mechanical engineering project for Urban Facilities
N.E. 10017
Electrical and Mechanical engineering project for Urban Facilities
ARV Arquitectos
Date: 2010
Paracuellos del Jarama, Madrid. Spain
Area: 14960 m²
Global budget: 567.842 €
Budget of the tasks undertaken: 290.448 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-10016-E-Technical assistance to the works at A30 Highway in Montreal. Definition, review and recalculation of auxiliary structures
N.E. 10016-E
Technical assistance to the works at A30 Highway in Montreal. Definition, review and recalculation of auxiliary structures
UTE A30CVJ ACCIONA + DRAGADOS
Date: 2010-2012
Montreal. Canada
Length: m
Global budget: 1200 MM €
Budget of the tasks undertaken: 25.000 €
Tasks undertaken: Studies and Reports. Detail Engineering. Technical assistance for building works. Recalculation and expert evaluation
3D3-10016-D-Technical assistance to the works at A30 Highway in Montreal. Bridge over Saint Laurence River assembly process study
N.E. 10016-D
Technical assistance to the works at A30 Highway in Montreal. Bridge over Saint Laurence River assembly process study
UTE A30CVJ ACCIONA + DRAGADOS
Date: 2010-2012
Montreal. Canada
Length: m
Global budget: 1200 MM €
Budget of the tasks undertaken: 25.000 €
Tasks undertaken: Studies and Reports. Detail Engineering. Technical assistance for building works. Recalculation and expert evaluation
3D3-10016-C-Technical assistance to the works at A30 Highway in Montreal. Structure lifting calculations
N.E. 10016-C
Technical assistance to the works at A30 Highway in Montreal. Structure lifting calculations
UTE A30CVJ ACCIONA + DRAGADOS
Date: 2010-2012
Montreal. Canada
Length: m
Global budget: 1200 MM €
Budget of the tasks undertaken: 25.000 €
Tasks undertaken: Studies and Reports. Detail Engineering. Technical assistance for building works. Recalculation and expert evaluation
3D3-10016-B-Technical assistance to the works at A30 Highway in Montreal. 
Toll plaza marquee structure review
N.E. 10016-B
Technical assistance to the works at A30 Highway in Montreal. Toll plaza marquee structure review
UTE A30CVJ ACCIONA + DRAGADOS
Date: 2012
Montreal. Canada
Area: 5835 m²
Global budget: 1200 MM €
Budget of the tasks undertaken: 390.000 €
Tasks undertaken: Studies and Reports. Detail Engineering. Project Review. Technical assistance for building works. Recalculation and expert evaluation
3D3-10016-A-Technical assistance to the works at A30 Highway in Montreal. Redefinition of linear & transversal drainage
N.E. 10016-A
Technical assistance to the works at A30 Highway in Montreal. Redefinition of linear & transversal drainage
UTE A30CVJ ACCIONA + DRAGADOS
Date: 2012
Montreal. Canada
Length: m
Global budget: 1200 MM €
Budget of the tasks undertaken:
Tasks undertaken: Studies and Reports. Technical assistance for building works. Recalculation and expert evaluation
3D3-10015-B-Technical assistance to the building works at A30 Highway in Montreal. Quantity surveying for reviewed structures
N.E. 10015-B
Technical assistance to the building works at A30 Highway in Montreal. Quantity surveying for reviewed structures
ACCIONA + DRAGADOS
Date: 2010
Montreal. Canada
Length: 6971 m
Global budget: 1200 MM €
Budget of the tasks undertaken:
Tasks undertaken: Studies and Reports. Detail Engineering. Technical assistance for building works. Recalculation and expert evaluation
3D3-10015-A-Technical assistance to the building works at A30 Highway in Montreal. Shop drawings review
N.E. 10015-A
Technical assistance to the building works at A30 Highway in Montreal. Shop drawings review
ACCIONA + DRAGADOS
Date: 2010
Montreal. Canada
Length: 6971 m
Global budget: 1200 MM €
Budget of the tasks undertaken:
Tasks undertaken: Studies and Reports. Detail Engineering. Technical assistance for building works. Recalculation and expert evaluation
3D3-10011-Prestressed beams checkings at Nouvelle Autoroute A-30 bridge over St Laurent River
N.E. 10011
Prestressed beams checkings at Nouvelle Autoroute A-30 bridge over St Laurent River
UTE A30CVJ ACCIONA + DRAGADOS
Date: 2010
Montreal. Canada
Length: 1863 m
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Recalculation and expert evaluation
3D3-10003-Structural engineering for seven solid waste treatment plants
N.E. 10003
Structural engineering for seven solid waste treatment plants
ACCIONA
Date: 2010
Extremadura. Spain
:
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09008-Civil engineering services for connection pathway at IKEA San Sebastian de los Reyes shop
N.E. 09008
Civil engineering services for connection pathway at IKEA San Sebastian de los Reyes shop
VECTOR XXI Arquitectos S.L.
Date: 2009
San Sebastián de los Reyes, Madrid. Spain
Length: 180 m
Global budget: 208.828..96 €
Budget of the tasks undertaken: 113.494 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08044-Recalculation of retaining walls and concrete slabs in subway under high speed train
N.E. 08044
Recalculation of retaining walls and concrete slabs in subway under high speed train
IMATHIA Construcción
Date: 2008
Sant Celoni, Barcelona. Spain
Area: 200 m²
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08043-Civil engineering services for infrastructure development of bike lanes
N.E. 08043
Civil engineering services for infrastructure development of bike lanes
Space Coop
Date: 2008
Madrid. Spain
Length: 2500 m
Global budget: 3699 MM €
Budget of the tasks undertaken: 67.833 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08029-Recalculation of retaining walls in N-320 road
N.E. 08029
Recalculation of retaining walls in N-320 road
IMATHIA Construcción
Date: 2008
Guadalajara. Spain
Length: 302 m
Global budget: 548.208.5.2 €
Budget of the tasks undertaken: 487.730 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-0742-Foundation engineering for viaduct in
N.E. 0742
Foundation engineering for viaduct in "Aguas Vivas"
ALDESA
Date: 2007
Guadalajara. Spain
Length: 155.3 m
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-0510-Structual engineering for noise barriers
N.E. 0510
Structual engineering for noise barriers
MVN Arquitectos
Date: 2005
Madrid. Spain
Length: 266 m
Global budget: 542.363..36 €
Budget of the tasks undertaken: 352.184 €
Tasks undertaken: Basic Engineering. Detail Engineering
 
 
3D3 INGENIERIA  C/Ramón de Aguinaga nº18 - Planta primera - 28028 Madrid (Spain) - proyectos@tresdetres.net - Tel: +34 91 591 52 42 - Fax: +34 915 94 37 59