3D3-17047-MEP Engineering for 12 row houses in Vallecas
N.E. 17047
MEP Engineering for 12 row houses in Vallecas
CANO Y ESCARIO Arquitectura
Date: 2017
Madrid, Spain
Area: 1794 m²
Global budget: WORK-IN-PR MM €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-17046-Structural Engineering for 26 row houses in Boadilla del Monte
N.E. 17046
Structural Engineering for 26 row houses in Boadilla del Monte
JAVIER FUSTER Arquitecto
Date: 2017
Madrid, Spain
Area: 6239 m²
Global budget: 5.734.250 €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-17034-Structural and M&E Engineering review for
N.E. 17034
Structural and M&E Engineering review for "Constitución de 1812" School
BUERAU VERITAS
Date: 2017
Leganés, Madrid. Spain
Area: 1429.9 m²
Global budget: 1.031.832 €
Budget of the tasks undertaken: 1.031.832 €
Tasks undertaken: Project Review
3D3-17032-MEP and Structural Engineering for residential building of 255 housing units in Espino del Cuquillo
N.E. 17032
MEP and Structural Engineering for residential building of 255 housing units in Espino del Cuquillo
Aranguren & Gallegos Arquitectos
Date: 2017
Alcobendas, Spain
Area: 52795 m²
Global budget: WORK-IN-PR MM €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken: Detail Engineering
3D3-17020-Architectural, MEP and Structural Engineering review and technical assistance for the refurbishment of an administrative Building in Cedaceros Street
N.E. 17020
Architectural, MEP and Structural Engineering review and technical assistance for the refurbishment of an administrative Building in Cedaceros Street
BUREAU VERITAS
Date: 2017
Madrid, Spain
Area: 2711 m²
Global budget: N/A €
Budget of the tasks undertaken: N/A €
Tasks undertaken: Project Review
3D3-17015-MEP and Structural Engineering for a residential building with 55 housing units in Vallecas
N.E. 17015
MEP and Structural Engineering for a residential building with 55 housing units in Vallecas
CANO Y ESCARIO Arquitectura
Date: 2017
Madrid, Spain
Area: 8853 m²
Global budget: 5.754.450 €
Budget of the tasks undertaken: 3.688.416 €
Tasks undertaken: Preliminary drafts. Basic Engineering. Detail Engineering
3D3-16029-Architectural and MEP Enginering for FREMAP Heath Care Center
N.E. 16029
Architectural and MEP Enginering for FREMAP Heath Care Center
FREMAP
Date: 2016-2017
Leon. Spain
Area: 1125 m²
Global budget: 950.000 €
Budget of the tasks undertaken: 950.000 €
Tasks undertaken: Preliminary drafts. Basic Engineering. Detail Engineering. Technical site management
3D3-16028-Architectural and MEP Enginering for FREMAP Heath Care Center
N.E. 16028
Architectural and MEP Enginering for FREMAP Heath Care Center
FREMAP
Date: 2016-2017
Valencia. Spain
Area: 325 m²
Global budget: 250.000 €
Budget of the tasks undertaken: 250.000 €
Tasks undertaken: Preliminary drafts. Basic Engineering. Detail Engineering. Technical site management
3D3-16015-Site management and Technical review of the Structural and MEP Engineering design for Diego Muñoz Primary School
N.E. 16015
Site management and Technical review of the Structural and MEP Engineering design for Diego Muñoz Primary School
BUREAU VERITAS
Date: 2016
Valdemoro, Madrid. Spain
Area: 3410 m²
Global budget: 1.902.086 €
Budget of the tasks undertaken: 1.067.495 €
Tasks undertaken: Project Review
3D3-16007.E-Structural and civil engineering for the storage complex
N.E. 16007.E
Structural and civil engineering for the storage complex "Naves de la Villa de Vicálvaro"
Excmo. Ayto. de Madrid
Date: 2016
Madrid. Spain
Area: 23600 m²
Global budget: 5.500.000 €
Budget of the tasks undertaken: 3.843.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-15042-Structural engineering for the  expansion of a four star NH Hotel
N.E. 15042
Structural engineering for the expansion of a four star NH Hotel
Aranguren & Gallegos Arquitectos
Date: 2015
Málaga. Spain
Area: 5360 m²
Global budget: 6.324.800 €
Budget of the tasks undertaken: 2.036.400 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-15037-Structural engineering for a residential building in San Romualdo Street
N.E. 15037
Structural engineering for a residential building in San Romualdo Street
José Carlos Rasines, Arquitecto
Date: 2015
Getafe, Madrid. Spain
Area: 14700 m²
Global budget: WORK-IN-PR MM €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-15009-Structural engineering and  technical assistance to building works for the rehabilitation of Evry2 Shopping Center
N.E. 15009
Structural engineering and technical assistance to building works for the rehabilitation of Evry2 Shopping Center
ACIEROID
Date: 2015
Évry, Île-de-France, France
Area: 1026 m²
Global budget: 2.052.000 €
Budget of the tasks undertaken: 461.700 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-15002-Structural drafting services for
N.E. 15002
Structural drafting services for "Ñuble" Subway Station
IDOM
Date: 2015
Santiago de Chile
Area: WORK-IN-PROGRESS m²
Global budget: 1.7.7. M$ €
Budget of the tasks undertaken: 5.3. M$ €
Tasks undertaken: Detail Engineering
3D3-14026-                 Structural engineering for
N.E. 14026
Structural engineering for "Estadio Nacional" Subway Station
IDOM
Date: 2014
Santiago de Chile
Area: WORK-IN-PROGRESS m²
Global budget: 2.6.8. M$ €
Budget of the tasks undertaken: 8.1. M$ €
Tasks undertaken: Detail Engineering
3D3-14019-Structural engineering for flour production plant
N.E. 14019
Structural engineering for flour production plant
EDHINOR
Date: 2014
Torrijos, Toledo. Spain
Area: WORK-IN-PROGRESS m²
Global budget: WORK-IN-PR MM €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken: Detail Engineering
3D3-14017-B-Structural engineering for
N.E. 14017-B
Structural engineering for "Los Leones Norte" Subway Station
IDOM
Date: 2014
Santiago de Chile. Chile
Area: 7850 m²
Global budget: 1.7.5. M$ €
Budget of the tasks undertaken: 5..25. M$ €
Tasks undertaken: Detail Engineering
3D3-14017-A-Structural engineering for
N.E. 14017-A
Structural engineering for "Ñuñoa" Subway Station
IDOM
Date: 2014
Santiago, Chile
Area: 12720 m²
Global budget: 2.2.5. M$ €
Budget of the tasks undertaken: 6..75. M$ €
Tasks undertaken: Detail Engineering
3D3-14010-Structural engineering for the building of the Social Security of Mérida
N.E. 14010
Structural engineering for the building of the Social Security of Mérida
EDHINOR
Date: 2014
Mérida, Badajoz. Spain
Area: WORK-IN-PROGRESS m²
Global budget: 3.669.200 €
Budget of the tasks undertaken: 420.000 €
Tasks undertaken: Basic Engineering. Detail Engineering. Technical assistance for building works
3D3-14009-Structural, mechanical and electrical enginering for El Bosco Pimary School
N.E. 14009
Structural, mechanical and electrical enginering for El Bosco Pimary School
AVR Arquitectos
Date: 2014-2015
Torrejón de Ardoz, Madrid. Spain
Area: 5250 m²
Global budget: 3.750.000 €
Budget of the tasks undertaken: 2.473.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-14006-Civil engineering for a 6MW photovoltaic power plant in Region de Arica y Parinacota, Chile
N.E. 14006
Civil engineering for a 6MW photovoltaic power plant in Region de Arica y Parinacota, Chile
SOLIDA Energias Renovables
Date: 2014
XV Region. Chile
Area: 240 m²
Global budget: N/A €
Budget of the tasks undertaken: N/A €
Tasks undertaken: Detail Engineering
3D3-13024-Structural engineering for a warehouse and offices building for REE
N.E. 13024
Structural engineering for a warehouse and offices building for REE
IDOM
Date: 2013
Menorca. Spain
Area: 928 m²
Global budget: 464.000 €
Budget of the tasks undertaken: 182.519 €
Tasks undertaken: Detail Engineering
3D3-13020-Recalculation of structure of an administrative building in Priego de Cordoba
N.E. 13020
Recalculation of structure of an administrative building in Priego de Cordoba
DRAGADOS
Date: 2013

Area: 3970 m²
Global budget: 4.210.000 €
Budget of the tasks undertaken: 1.288.664 €
Tasks undertaken: Recalculation and expert evaluation
3D3-13017-Recalculation of structure for the facilities building EQ+I
N.E. 13017
Recalculation of structure for the facilities building EQ+I
DRAGADOS
Date: 2013

Area: 2750 m²
Global budget: 2.100.000 €
Budget of the tasks undertaken: 705.000 €
Tasks undertaken: Studies and Reports. Recalculation and expert evaluation
3D3-13011-Structual engineering for seven stormwater detention vaults
N.E. 13011
Structual engineering for seven stormwater detention vaults
ACCIONA Infraestructuras
Date: 2013
Ferrol, La Coruña. Spain
Area: 11387 m²
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Detail Engineering. Recalculation and expert evaluation
3D3-13010-Review of the panels supporting structure in a photovoltaic park in Letsedi, South Africa
N.E. 13010
Review of the panels supporting structure in a photovoltaic park in Letsedi, South Africa
SOLIDA Energias Renovables
Date: 2013
Letsedi. South Africa
:
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Studies and Reports
3D3-13008-M&E engineering and structural engineering for the request for tenders for a Contemporary Art Museum in Assilah
N.E. 13008
M&E engineering and structural engineering for the request for tenders for a Contemporary Art Museum in Assilah
Hernandez de Leon & Alvaro Siza, Arquitectos
Date: 2013
Assilah. Morocco
Area: 9189 m²
Global budget: 4..0 M.M € €
Budget of the tasks undertaken: 2..8 M.M € €
Tasks undertaken: Preliminary drafts
3D3-13006-C-Civil Engineering for Kaxu Solar One thermosolar plant in Northern Cape, South Africa. Solar Field Electrical Buildings
N.E. 13006-C
Civil Engineering for Kaxu Solar One thermosolar plant in Northern Cape, South Africa. Solar Field Electrical Buildings
ABEINSA
Date: 2013
Kaxu. South Africa
Area: 80.000 m2 m²
Global budget: 589. M$ €
Budget of the tasks undertaken:
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-13006-B-Civil Engineering for Kaxu Solar One thermosolar plant in Northern Cape, South Africa. Electrical Buildings
N.E. 13006-B
Civil Engineering for Kaxu Solar One thermosolar plant in Northern Cape, South Africa. Electrical Buildings
ABEINSA
Date: 2013
Kaxu. South Africa
Area: 80.000 m2 m²
Global budget: 589. M$ €
Budget of the tasks undertaken:
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-13004-Civil Engineering services for thermosolar plant in Almeria
N.E. 13004
Civil Engineering services for thermosolar plant in Almeria
SOLIDA Energias Renovables
Date: 2013
Almería. Spain
Area: 10722 m²
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Detail Engineering
3D3-12020-Foundation engineering for 24 wind turbines
N.E. 12020
Foundation engineering for 24 wind turbines
SOLIDA Energias Renovables
Date: 2012
Gravina di Puglia. Italy
:
Global budget:
Budget of the tasks undertaken: 1447645.89 MM €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-12017-Civil engineering preliminary draft for extension of CCGT Barranco III
N.E. 12017
Civil engineering preliminary draft for extension of CCGT Barranco III
IDOM
Date: 2012
Gran Canaria. Spain
Area: 16577 m²
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Preliminary drafts. Basic Engineering
3D3-12015-B-Civil and structural engineering services for biomass power plant in Ghana
N.E. 12015-B
Civil and structural engineering services for biomass power plant in Ghana
POYRY - HEYMO
Date: 2012
Atebubu. Ghana
Area: WORK-IN-PROGRESS m²
Global budget: WORK-IN-PR MM €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-12015-A-Civil and structural engineering services for Vopak industrial plant enlargement
N.E. 12015-A
Civil and structural engineering services for Vopak industrial plant enlargement
POYRY - HEYMO
Date: 2012
Callao. Peru
Area: WORK-IN-PROGRESS m²
Global budget: WORK-IN-PR MM €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-12012E-Structural engineering for Iesu Communio church building
N.E. 12012E
Structural engineering for Iesu Communio church building
Julián Fernández, Arquitecto
Date: 2012
Aranda de Duero, Burgos. Spain
Area: 2439 m²
Global budget: 1.275.000 €
Budget of the tasks undertaken: 317.300 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-12011-Civil engineering services for biomass generation plant
N.E. 12011
Civil engineering services for biomass generation plant
SOLIDA Energias Renovables
Date: 2012
San Pedro de Macorís. Dominican Republic
Area: WORK-IN-PROGRESS m²
Global budget: WORK-IN-PR MM €
Budget of the tasks undertaken: WORK-IN-PR MM €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-12008-Structural engineering and technical assistance to building works for the rehabilitation of a residential building in Relatores Street
N.E. 12008
Structural engineering and technical assistance to building works for the rehabilitation of a residential building in Relatores Street
Fernando García, Arquitecto
Date: 2012
Madrid. Spain
Area: 516 m²
Global budget: 246.648 €
Budget of the tasks undertaken: 75.677 €
Tasks undertaken: Basic Engineering. Detail Engineering. Technical assistance for building works. Recalculation and expert evaluation
3D3-11017-Structural survey, construction project and technical site management in the remodeling of the electrical substation ST Cáceres III
N.E. 11017
Structural survey, construction project and technical site management in the remodeling of the electrical substation ST Cáceres III
Iberdrola Ingeniería y Construcción
Date: 2011-2016
Cáceres. Spain
Area: 483 m²
Global budget: 450.000 €
Budget of the tasks undertaken: 450.000 €
Tasks undertaken: Studies and Reports. Basic Engineering. Detail Engineering. Technical site management
3D3-11015-Technical site management in the remodeling of the electrical substation ST San Felipe
N.E. 11015
Technical site management in the remodeling of the electrical substation ST San Felipe
Iberdrola Ingeniería y Construcción
Date: 2011
Madrid. Spain
Area: 2388 m²
Global budget: 165.951 €
Budget of the tasks undertaken: 165.951 €
Tasks undertaken: Technical site management
3D3-11014-Structural engineering services in the remodeling of the electrical substation ST San Felipe
N.E. 11014
Structural engineering services in the remodeling of the electrical substation ST San Felipe
Iberdrola Ingeniería y Construcción
Date: 2011
Madrid. Spain
Area: 2388 m²
Global budget: 165.951 €
Budget of the tasks undertaken: 165.951 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-11013-Structural engineering for a residential building with 41 housing units
N.E. 11013
Structural engineering for a residential building with 41 housing units
VECTOR XXI Arquitectos S.L.
Date: 2011
Los Coronales, Madrid. Spain
Area: 13345 m²
Global budget: 7.833.515 €
Budget of the tasks undertaken: 1.131.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-11011-Structural engineering services and technical site management in the remodeling of the electrical substation ST Argüelles
N.E. 11011
Structural engineering services and technical site management in the remodeling of the electrical substation ST Argüelles
Iberdrola Ingeniería y Construcción
Date: 2011
Madrid. Spain
Area: 862 m²
Global budget: 760.000 €
Budget of the tasks undertaken: 760.000 €
Tasks undertaken: Project Review. Technical site management. Recalculation and expert evaluation
3D3-11009-Structural engineering for a warehouse for train maintenance
N.E. 11009
Structural engineering for a warehouse for train maintenance
IDP Ingenieros
Date: 2011
Tenerife. Spain
Area: 18300 m²
Global budget: 7.722.600 €
Budget of the tasks undertaken: 3.329.105 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-11002E-Structural engineering for an industrial building used as Data Center
N.E. 11002E
Structural engineering for an industrial building used as Data Center
Arquitectura Norte S.L.
Date: 2010
Madrid. Spain
Area: 6714 m²
Global budget: 6.183.594 €
Budget of the tasks undertaken: 2.121.624 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-10024-Structural engineering for the remodeling of Cervantes Theatre
N.E. 10024
Structural engineering for the remodeling of Cervantes Theatre
Héctor León, Arquitecto
Date: 2010
Segovia. Spain
Area: 5200 m²
Global budget: 4.789.200 €
Budget of the tasks undertaken: 1.321.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-10019E-Structural engineering for an R & D & I building at Salamanca University
N.E. 10019E
Structural engineering for an R & D & I building at Salamanca University
EDHINOR
Date: 2010
Salamanca, Spain
Area: 12000 m²
Global budget: 8.100.000 €
Budget of the tasks undertaken: 2.110.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-10014-Recalculation of structure for Bank of Spain building in Pontevedra
N.E. 10014
Recalculation of structure for Bank of Spain building in Pontevedra
EDHINOR
Date: 2010
Pontevedra. Spain
Area: 2700 m²
Global budget: 2.000.700 €
Budget of the tasks undertaken: 510.300 €
Tasks undertaken: Basic Engineering. Detail Engineering. Recalculation and expert evaluation
3D3-10010E-Structural engineering services for accomplishing the bidding conditions of Parque Huelin underground parking
N.E. 10010E
Structural engineering services for accomplishing the bidding conditions of Parque Huelin underground parking
CONTRAT S.A.
Date: 2010
Malaga. Spain
Area: 8400 m²
Global budget: 4.400.000 €
Budget of the tasks undertaken: 2.350.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-10010-Civil engineering services for accomplishing the bidding conditions of Parque Huelin underground parking
N.E. 10010
Civil engineering services for accomplishing the bidding conditions of Parque Huelin underground parking
CONTRAT S.A.
Date: 2010
Malaga. Spain
Area: 8400 m²
Global budget: 4.400.000 €
Budget of the tasks undertaken: 4.400.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-10006-Structural drafting services for Higher Study Building & Public Committee of Tripoli
N.E. 10006
Structural drafting services for Higher Study Building & Public Committee of Tripoli
IDOM
Date: 2010
Tripoli. Lybia
Area: 44000 m²
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-10003-Structural engineering for seven solid waste treatment plants
N.E. 10003
Structural engineering for seven solid waste treatment plants
ACCIONA
Date: 2010
Extremadura. Spain
:
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-10001-CAM-Structural engineering for chamber hall at the International Centre of Vitoria
N.E. 10001-CAM
Structural engineering for chamber hall at the International Centre of Vitoria
ETESA
Date: 2010
Vitoria. Spain
Area: 4200 m²
Global budget: 5.229.000 €
Budget of the tasks undertaken: 1.138.200 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-10001-SIN-Structural engineering for philharmonic hall at the International Centre of Vitoria
N.E. 10001-SIN
Structural engineering for philharmonic hall at the International Centre of Vitoria
Bayón Arquitectos ETESA
Date: 2010
Vitoria. Spain
Area: 12300 m²
Global budget: 19.003.500 €
Budget of the tasks undertaken: 7.023.300 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09028E-Structural engineering for hangar of the Traffic Department at Seville Airport
N.E. 09028E
Structural engineering for hangar of the Traffic Department at Seville Airport
Tekia Ingenieros
Date: 2009
Seville. Spain
Area: 1495 m²
Global budget: 840.000 €
Budget of the tasks undertaken: 365.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09027-Recalculation of structure and technical assistance to building works for a Social Security building in Vitoria
N.E. 09027
Recalculation of structure and technical assistance to building works for a Social Security building in Vitoria
EDHINOR
Date: 2009-2011
Vitoria. Spain
Area: 16400 m²
Global budget: 16.356.000 €
Budget of the tasks undertaken: 2.912.000 €
Tasks undertaken: Basic Engineering. Detail Engineering. Recalculation and expert evaluation
3D3-09022-Mechanical, electrical and structural engineering for the remodeling of eight offices in Tribeca Business Park
N.E. 09022
Mechanical, electrical and structural engineering for the remodeling of eight offices in Tribeca Business Park
COOT Arquitectos
Date: 2009
Alcobendas, Madrid. Spain
Area: 3316 m²
Global budget: 497.400 €
Budget of the tasks undertaken: 175.795 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09019-Structural engineering for a retirement home
N.E. 09019
Structural engineering for a retirement home
DMO Arquitectos
Date: 2010-2011
Teruel. Spain
Area: 2264 m²
Global budget: 1.616.496 €
Budget of the tasks undertaken: 552.459 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09017E-Structural engineering for City hall building of Aldea del Fresno
N.E. 09017E
Structural engineering for City hall building of Aldea del Fresno
COOT Arquitectos
Date: 2009
Aldea del Fresno, Madrid. Spain
Area: 795 m²
Global budget: 628.845 €
Budget of the tasks undertaken: 137.530 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09016-Structural engineering for the remodeling of a sanitary building in Doctor Castelo street
N.E. 09016
Structural engineering for the remodeling of a sanitary building in Doctor Castelo street
Elena Blanco, Arquitecto
Date: 2009
Madrid. Spain
Area: 2241 m²
Global budget: 719.361 €
Budget of the tasks undertaken: 118.362 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09014-Mechanical, electrical and structural engineering for services building in Son Reus Power Plant
N.E. 09014
Mechanical, electrical and structural engineering for services building in Son Reus Power Plant
IMPLANTA
Date: 2009
Palma de Mallorca. Spain
Area: 716 m²
Global budget: 396.664 €
Budget of the tasks undertaken: 179.012 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09013-Civil engineering services for cogeneration plant
N.E. 09013
Civil engineering services for cogeneration plant
OTSI
Date: 2009
Dos Hermanas, Sevilla. Spain
Area: 1175 m²
Global budget: 217.375 €
Budget of the tasks undertaken: 217.375 €
Tasks undertaken: Basic Engineering. Detail Engineering. Project Review
3D3-09012-Structural engineering for a residential building with 107 state subsidised housing units
N.E. 09012
Structural engineering for a residential building with 107 state subsidised housing units
Nadal y Fernandez, arquitectos
Date: 2009
Vallecas, Madrid. Spain
Area: 9435 m²
Global budget: 4.899.453 €
Budget of the tasks undertaken: 1.553.907 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09011-Structural engineering for the review of construction plans, audit report and structural reinforcement for an apartment building in Palos de la Frontera street
N.E. 09011
Structural engineering for the review of construction plans, audit report and structural reinforcement for an apartment building in Palos de la Frontera street
Mario Curto
Date: 2009
Madrid. Spain
Area: 10098 m²
Global budget: 6.169.878 €
Budget of the tasks undertaken: 296.990 €
Tasks undertaken: Basic Engineering. Detail Engineering. Recalculation and expert evaluation
3D3-09008-Civil engineering services for connection pathway at IKEA San Sebastian de los Reyes shop
N.E. 09008
Civil engineering services for connection pathway at IKEA San Sebastian de los Reyes shop
VECTOR XXI Arquitectos S.L.
Date: 2009
San Sebastián de los Reyes, Madrid. Spain
Length: 180 m
Global budget: 208.828..96 €
Budget of the tasks undertaken: 113.494 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09007-Structural engineering and technical assistance to building works of Supercor® Supermarket in Calle Toledo
N.E. 09007
Structural engineering and technical assistance to building works of Supercor® Supermarket in Calle Toledo
IDOM
Date: 2009
Madrid. Spain
Area: 2210 m²
Global budget: 2.274.245 €
Budget of the tasks undertaken: 1.609.427 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09006-Structural engineering for gymnasium building in San Juan Bosco School
N.E. 09006
Structural engineering for gymnasium building in San Juan Bosco School
ARV Arquitectos
Date: 2009
Torrejón de Ardoz, Madrid. Spain
Area: 259 m²
Global budget: 159.026 €
Budget of the tasks undertaken: 67.530 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-09005-Structural survey, construction project and technical site management in the remodeling of the electrical substation ST Viveros
N.E. 09005
Structural survey, construction project and technical site management in the remodeling of the electrical substation ST Viveros
Iberdrola Ingeniería y Construcción
Date: 2009
Valencia. Spain
Area: 6520 m²
Global budget: 485.390 €
Budget of the tasks undertaken: 485.390 €
Tasks undertaken: Basic Engineering. Detail Engineering. Project Review
3D3-09002-Recalculation of steel canopies at the airport parking of Vitoria airport
N.E. 09002
Recalculation of steel canopies at the airport parking of Vitoria airport
EUROCONSULT
Date: 2009
Vitoria. Spain
Area: 2157.5 m²
Global budget: 564.950 €
Budget of the tasks undertaken: 564.950 €
Tasks undertaken: Basic Engineering. Detail Engineering. Recalculation and expert evaluation
3D3-08045-Structural engineering for Meeting Point pavilion
N.E. 08045
Structural engineering for Meeting Point pavilion
Iglesias-Hamelin, arquitectos
Date: 2008
Madrid, Spain.
Area: 325 m²
Global budget: 248.625 €
Budget of the tasks undertaken: 122.136 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08044-Recalculation of retaining walls and concrete slabs in subway under high speed train
N.E. 08044
Recalculation of retaining walls and concrete slabs in subway under high speed train
IMATHIA Construcción
Date: 2008
Sant Celoni, Barcelona. Spain
Area: 200 m²
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08043-Civil engineering services for infrastructure development of bike lanes
N.E. 08043
Civil engineering services for infrastructure development of bike lanes
Space Coop
Date: 2008
Madrid. Spain
Length: 2500 m
Global budget: 3699 MM €
Budget of the tasks undertaken: 67.833 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08042-Feasability study for the supporting of medium voltage switchgear in an existing electrical substation ST San Felipe
N.E. 08042
Feasability study for the supporting of medium voltage switchgear in an existing electrical substation ST San Felipe
Iberdrola Ingeniería y Construcción
Date: 2008
Madrid. Spain
Area: 360 m²
Global budget:
Budget of the tasks undertaken:
Tasks undertaken: Basic Engineering. Detail Engineering. Recalculation and expert evaluation
3D3-08041-Structural engineering for the enlargement and rehabilitation of the Bank of Spain building
N.E. 08041
Structural engineering for the enlargement and rehabilitation of the Bank of Spain building
EDHINOR
Date: 2008
Palencia. Spain
Area: 622 m²
Global budget: 551.714 €
Budget of the tasks undertaken: 53.611 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08040-Structural engineering for a warehouse and office block for IKEA
N.E. 08040
Structural engineering for a warehouse and office block for IKEA
VECTOR XXI Arquitectos S.L.
Date: 2008
San Sebastián de los Reyes, Madrid. Spain
Area: 8500 m²
Global budget: 4.139.500 €
Budget of the tasks undertaken: 2.611.713 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08039-Structural engineering for the City Hall of Quintanar del Rey
N.E. 08039
Structural engineering for the City Hall of Quintanar del Rey
Nadal y Fernandez, arquitectos
Date: 2008
Quintanar del Rey, Albacete. Spain
Area: 2469 m²
Global budget: 1.755.459 €
Budget of the tasks undertaken: 277.224 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08037-Structural engineering for a 98-room ETAP hotel
N.E. 08037
Structural engineering for a 98-room ETAP hotel
AR Arquitectos
Date: 2008
Vallecas, Madrid. Spain
Area: 4600 m²
Global budget: 2.396.600 €
Budget of the tasks undertaken: 542.690 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08034-Structural engineering for rehabilitation of hostel for pilgrims on the Camino de Santiago
N.E. 08034
Structural engineering for rehabilitation of hostel for pilgrims on the Camino de Santiago
Pedro Quero, Arquitecto
Date: 2008
Pendueles, Asturias. Spain
Area: 212 m²
Global budget: 87.980 €
Budget of the tasks undertaken: 18.325 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08033-Structural engineering for a residential building complex with 420 state subsidised housing units
N.E. 08033
Structural engineering for a residential building complex with 420 state subsidised housing units
Carlos Ballesteros, Arquitecto
Date: 2008
Valdevebas, Madrid. Spain
Area: 47100 m²
Global budget: 24.539.100 €
Budget of the tasks undertaken: 8.512.192 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08032-Structural engineering for a residential building with 122 state subsidised housing units
N.E. 08032
Structural engineering for a residential building with 122 state subsidised housing units
AR Arquitectos
Date: 2008
Alcalá de Henares, Madrid. Spain
Area: 16246 m²
Global budget: 9.975.044 €
Budget of the tasks undertaken: 3.167.970 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08030-Structural engineering for Sanchinarro Market
N.E. 08030
Structural engineering for Sanchinarro Market
MUTE Arquitectectura
Date: 2008
Madrid. Spain
Area: 25970 m²
Global budget: 21.087.640 €
Budget of the tasks undertaken: 4.539.962 €
Tasks undertaken: Preliminary drafts. Basic Engineering
3D3-08029-Recalculation of retaining walls in N-320 road
N.E. 08029
Recalculation of retaining walls in N-320 road
IMATHIA Construcción
Date: 2008
Guadalajara. Spain
Length: 302 m
Global budget: 548.208.5.2 €
Budget of the tasks undertaken: 487.730 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08028-Structural engineering for 22-storey residential building
N.E. 08028
Structural engineering for 22-storey residential building
PROMHOGAR
Date: 2008
Alcalá de Henares, Madrid. Spain
Area: 13785 m²
Global budget: 9.925.200 €
Budget of the tasks undertaken: 1.595.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08026-Structural engineering for the extension of Marqués de Griñón winery
N.E. 08026
Structural engineering for the extension of Marqués de Griñón winery
ALFATEC
Date: 2008
Toledo. Spain
Area: 2100 m²
Global budget: 875.700 €
Budget of the tasks undertaken: 317.833 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08025-Structural engineering for a residential building with 49 state subsidised housing units
N.E. 08025
Structural engineering for a residential building with 49 state subsidised housing units
David Nadal, Arquitecto
Date: 2008
Valdelaguna, Madrid. Spain
Area: 5298 m²
Global budget: 2.760.258 €
Budget of the tasks undertaken: 794.842 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08023-Civil engineering for a photovoltaic panel manufacturing facility
N.E. 08023
Civil engineering for a photovoltaic panel manufacturing facility
HEYMO
Date: 2008
Cádiz. Spain
Area: 11150 m²
Global budget: 5.285.100 €
Budget of the tasks undertaken: 5.285.100 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08021-Structural engineering for a building with 81 state subsidised housing units, offices and car parking
N.E. 08021
Structural engineering for a building with 81 state subsidised housing units, offices and car parking
MAE Arquitectos
Date: 2008
Guadalajara. Spain
Area: 14857 m²
Global budget: 8.765.630 €
Budget of the tasks undertaken: 1.920.525 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08020-Structural design for the enlargement of a school
N.E. 08020
Structural design for the enlargement of a school
G2R Arquitectos
Date: 2008
Villarubia de Santiago, Toledo. Spain
Area: 205 m²
Global budget: 187.370 €
Budget of the tasks undertaken: 112.926 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08016-Structural engineering for warehouse for Klinston Building and Tunnel at CERN
N.E. 08016
Structural engineering for warehouse for Klinston Building and Tunnel at CERN
IDOM
Date: 2008
Geneva, Switzerland
Area: 2445 m²
Global budget: 1.564.800 €
Budget of the tasks undertaken: 1.105.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08014-Structural engineering for 135 terraced houses
N.E. 08014
Structural engineering for 135 terraced houses
VECTOR XXI Arquitectos S.L.
Date: 2008
Zapateira, La Coruña. Spain
Area: 22900 m²
Global budget: 14.885.000 €
Budget of the tasks undertaken: 5.667.996 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08010-Structural engineering for ALEPH school
N.E. 08010
Structural engineering for ALEPH school
MVN Arquitectos
Date: 2008
Madrid, Spain
Area: 1188 m²
Global budget: 819.720 €
Budget of the tasks undertaken: 256.355 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08009-Structural engineering for fruit juices and ecological ink facility
N.E. 08009
Structural engineering for fruit juices and ecological ink facility
IDOM
Date: 2008
Manzanares, Ciudad Real. Spain
Area: 3650 m²
Global budget: 733.660 €
Budget of the tasks undertaken: 733.660 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08008-Structural engineering for Phase II of Rivas City Central Library
N.E. 08008
Structural engineering for Phase II of Rivas City Central Library
ARV Arquitectos
Date: 2008
ivas Vaciamadrid, Madrid. Spain
Area: 2040 m²
Global budget: 1.468.800 €
Budget of the tasks undertaken: 380.200 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08007-Structural engineering for the Central Police Station of Móstoles
N.E. 08007
Structural engineering for the Central Police Station of Móstoles
Miguel Ángel Baños, Arquitecto
Date: 2008
Móstoles, Madrid. Spain
Area: 10230 m²
Global budget: 5.984.550 €
Budget of the tasks undertaken: 1.447.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08006-TWR-Structural engineering checkings and technical assistance to the building works for the Pamplona Noain Airport new control tower
N.E. 08006-TWR
Structural engineering checkings and technical assistance to the building works for the Pamplona Noain Airport new control tower
INECO-AENA
Date: 2008
Pamplona. Spain
Area: 1953 m²
Global budget: 4.500.000 €
Budget of the tasks undertaken: 1.150.000 €
Tasks undertaken: Basic Engineering. Detail Engineering. Technical assistance for building works. Recalculation and expert evaluation
3D3-08006-NAT-Structural engineering checkings and technical assistance to the building works for the new terminal area of Pamplona Noain Airport
N.E. 08006-NAT
Structural engineering checkings and technical assistance to the building works for the new terminal area of Pamplona Noain Airport
AENA
Date: 2008
Pamplona. Spain
Area: 11200 m²
Global budget: 22.900.000 €
Budget of the tasks undertaken: 5.130.000 €
Tasks undertaken: Basic Engineering. Detail Engineering. Technical assistance for building works. Recalculation and expert evaluation
3D3-08005-Structural engineering for desalination plant
N.E. 08005
Structural engineering for desalination plant
ACCIONA
Date: 2008
Telde, Gran Canaria. Spain
Area: 3400 m²
Global budget: 708.584 €
Budget of the tasks undertaken: 708.584 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08004-Structural engineering for a residential building complex with 152 state subsidised housing units
N.E. 08004
Structural engineering for a residential building complex with 152 state subsidised housing units
AR Arquitectos
Date: 2008
Valdebebas, Madrid. Spain
Area: 16300 m²
Global budget: 9.454.000 €
Budget of the tasks undertaken: 4.133.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08003-Civil engineering services for CEUTA13 gas turbine building
N.E. 08003
Civil engineering services for CEUTA13 gas turbine building
OTSI - ENDESA
Date: 2008
Ceuta. Spain
Area: 1585 m²
Global budget: 594.375 €
Budget of the tasks undertaken: 594.375 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08002-Structural design for the enlargement of a school
N.E. 08002
Structural design for the enlargement of a school
G2R Arquitectura
Date: 2008
Las Lomas, Guadalajara. Spain
Area: 995 m²
Global budget: 646.750 €
Budget of the tasks undertaken: 185.685 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-08001-Mechanical, electrical and structural engineering for remodeling a service building in Lanzarote Airport
N.E. 08001
Mechanical, electrical and structural engineering for remodeling a service building in Lanzarote Airport
IDOM - AENA
Date: 2008
Lanzarote, Las Palmas. Spain
Area: 280 m²
Global budget: 1.008.000 €
Budget of the tasks undertaken: 1.008.000 €
Tasks undertaken: Basic Engineering. Detail Engineering
3D3-0766-Foundation engineering and technical site management for underpinning of residential building
N.E. 0766
Foundation engineering and technical site management for underpinning of residential building
DMO Arquitectos
Date: 2007
Vallecas, Madrid. Spain
Area: 1016 m²
Global budget: 14.933 €
Budget of the tasks undertaken: 14.933 €
Tasks undertaken: Basic Engineering. Detail Engineering
 
 
3D3 INGENIERIA  C/Ramón de Aguinaga nº18 - Planta primera - 28028 Madrid (Spain) - proyectos@tresdetres.net - Tel: +34 91 591 52 42 - Fax: +34 915 94 37 59